Campbell School Construction
Campbell Project HOMEarchWork In Progress
 

MORE CONSTRUCTION IMAGES - August 25, 2009
Building interior demolition continuing with the demolition of an interior stairwell to make room for the main office. Concrete pours started on the second floor to prepare floor for finishes. Ductwork for ventilation system on site and installation started.

- Click on thumbnails for larger view. Opens in a new window -

 

Greater Essex County District School Board        BUILDING TOMORROW TODAY